HomeContract LawDamages: remoteness, causation and mitigation

Contract Law · FLK1

Damages: remoteness, causation and mitigation: SQE1 practice questions

15 single best answer questions on damages: remoteness, causation and mitigation, with the answer explained and the law behind each one.

Practise Damages: remoteness, causation and mitigation

15 questions. Choose an answer, check it, and read the law behind it. Your place is saved in this browser.

Keyboard: press 1 to 5 (or A to E) to choose, Enter to check or continue.

Law covered in these questions

  • Hadley v Baxendale (1854) 9 Exch 341
  • Victoria Laundry (Windsor) Ltd v Newman Industries Ltd [1949] 2 KB 528
  • Transfield Shipping Inc v Mercator Shipping Inc (The Achilleas) [2008] UKHL 48
  • Koufos v C Czarnikow Ltd (The Heron II) [1969] 1 AC 350
  • H Parsons (Livestock) Ltd v Uttley Ingham & Co Ltd [1978] QB 791
  • Wellesley Partners LLP v Withers LLP [2015] EWCA Civ 1146
  • British Westinghouse Electric and Manufacturing Co Ltd v Underground Electric Railways Co of London Ltd [1912] AC 673
  • Payzu Ltd v Saunders [1919] 2 KB 581
  • Pilkington v Wood [1953] Ch 770
  • Banco de Portugal v Waterlow & Sons Ltd [1932] AC 452
  • Quinn v Burch Bros (Builders) Ltd [1966] 2 QB 370
  • Barclays Bank plc v Fairclough Building Ltd [1995] QB 214
  • Law Reform (Contributory Negligence) Act 1945, s 1
  • Lambert v Lewis [1982] AC 225

All 15 questions with answers

Try them above first, then read the worked answers below.

Question 1 · Damages: remoteness, causation and mitigationDraft, pending solicitor review

Vector Ltd, a printing business, contracted to buy a specialised machine from Ruka Ltd for £40,000, to be delivered on 1 June. Ruka delivered six weeks late, in breach. Ruka knew Vector was a printing business but did not know that Vector had won a one-off, unusually lucrative contract that depended on the machine. Vector lost its normal profits from ordinary printing work during the delay, and also the exceptional profit on the one-off contract. Which statement best describes the recoverable loss?

  1. Vector can recover neither loss, because lost profits are always too remote in contract.
  2. Vector can recover neither loss unless Ruka expressly agreed in the contract to be liable for lost profits.
  3. Vector can recover both losses if they were foreseeable at the date of the breach, rather than at the date of the contract.
  4. Vector can recover both losses, because both were factually caused by the breach.
  5. Vector can recover its normal lost profits, but can recover the exceptional profit only if the special circumstances were within the parties' contemplation when the contract was made.Correct answer
Question 2 · Damages: remoteness, causation and mitigationDraft, pending solicitor review

Kip's mill was stopped because its crankshaft broke. He sent it with a carrier to engineers in Greenwich to be copied, but did not tell the carrier that the mill could not work without it. The carrier delayed delivery by several days, and Kip lost profits during that time. Which of the following best describes Kip's claim for lost profits?

  1. He recovers lost profits, because the delay was a breach of contract.
  2. He recovers half his lost profits, reflecting the carrier's partial fault.
  3. He recovers lost profits, because mills ordinarily stop without crankshafts.
  4. He cannot recover lost profits, because carriers are never liable for delay.
  5. He cannot recover lost profits, as they were too remote.Correct answer
Question 3 · Damages: remoteness, causation and mitigationDraft, pending solicitor review

Lark Laundries bought a large boiler from Mint Engineering for its expanding business, Mint knowing Lark wanted it for immediate use. Mint delivered five months late. Lark lost ordinary profits during the delay and also lost exceptionally lucrative dyeing contracts with a government department, of which Mint knew nothing. Which of the following best describes Lark's recovery?

  1. Lark recovers all its lost profits, because Mint knew of the need for immediate use.
  2. Lark recovers nothing, because lost profits are always too remote.
  3. Lark recovers ordinary lost profits, but not the dyeing contract profits.Correct answer
  4. Lark recovers the dyeing contract profits only, as they were the main loss.
  5. Lark recovers only the difference in value of the boiler at the two dates.
Question 4 · Damages: remoteness, causation and mitigationDraft, pending solicitor review

Nova chartered Oslo's ship to carry sugar to Basrah, where Nova intended to sell it. In breach, Oslo deviated and arrived nine days late. In the meantime, the market price of sugar at Basrah fell. Oslo did not know Nova intended to sell immediately, but knew there was a sugar market at Basrah. Nova claims the fall in price. Which of the following best describes the position?

  1. Nova cannot recover, because market price falls are inherently unpredictable.
  2. Nova recovers the fall in price, as it was a not unlikely result of delay.Correct answer
  3. Nova cannot recover, because Oslo did not know Nova meant to sell on arrival.
  4. Nova recovers the fall in price, but only if it was reasonably foreseeable.
  5. Nova cannot recover, because the deviation was not a breach of contract.
Question 5 · Damages: remoteness, causation and mitigationDraft, pending solicitor review

Pip, a pig farmer, bought a bulk food hopper from Quay Ltd, which installed it with the ventilator sealed. As a result, the pig nuts went mouldy. Many pigs fell ill with a rare intestinal infection and 254 died. Quay argues that, although some illness was foreseeable, it could not have contemplated such a serious infection. Which of the following best describes the position?

  1. Quay is not liable, because the extent of the illness was not contemplated.
  2. Quay is not liable, because the infection was rare and unpredictable.
  3. Quay is not liable, because death of livestock is always too remote.
  4. Quay is liable only for the cost of the mouldy food, not the pigs.
  5. Quay is liable, as illness of the pigs was the type of loss contemplated.Correct answer
Question 6 · Damages: remoteness, causation and mitigationDraft, pending solicitor review

Rho Shipping chartered its vessel to Sigma Lines, with redelivery due by 2 May. Sigma redelivered nine days late. Because of the delay, Rho lost a lucrative follow-on charter it had fixed with another charterer, at a time when market rates were falling sharply. Rho claims the loss on the follow-on charter. Market understanding was that charterers were liable only for the difference between market and charter rates during the overrun. Which of the following best describes the position?

  1. Rho recovers the full loss on the follow-on charter, as it was foreseeable.
  2. Rho recovers nothing, because late redelivery is not a breach of charter.
  3. Rho recovers only the overrun loss, as Sigma did not assume more.Correct answer
  4. Rho recovers the follow-on loss, because Sigma knew of Rho's other fixture.
  5. Rho recovers half the follow-on loss, reflecting the volatile market.
Question 7 · Damages: remoteness, causation and mitigationDraft, pending solicitor review

Tilia Partners, an executive recruitment firm, was formed in reliance on negligent advice from its solicitors about its partnership agreement, which forced it to buy out a partner early. Tilia claims lost profits, including profits on a very lucrative contract with a large bank that the solicitors could not have contemplated. The solicitors owed duties in both contract and tort. Which remoteness test applies?

  1. The tort test of reasonable foreseeability, as it is more generous to Tilia.
  2. The contractual test of reasonable contemplation.Correct answer
  3. Whichever test Tilia chooses, because it may elect between contract and tort.
  4. The tort test, because the solicitors' breach consisted of negligent advice.
  5. No remoteness test, because professional negligence is strictly liable.
Question 8 · Damages: remoteness, causation and mitigationDraft, pending solicitor review

Ulla bought turbines from Vega Engineering for her power station. They were defective and inefficient, in breach of contract. Ulla reasonably replaced them with new turbines of a more efficient type, which saved her more in running costs than the new turbines cost. She claims the cost of the replacements from Vega. Which of the following best describes the position?

  1. Ulla recovers the full replacement cost, because the breach caused her to buy them.
  2. Ulla recovers the replacement cost, but only after the original turbines failed.
  3. Ulla recovers nothing, because she chose to buy more efficient turbines.
  4. Ulla's damages are reduced by the savings that flowed from her mitigation.Correct answer
  5. Ulla recovers the difference between the old and new turbine prices.
Question 9 · Damages: remoteness, causation and mitigationDraft, pending solicitor review

Wix Ltd agreed to buy silk from Yarn Ltd in instalments, payment within one month of delivery. After Wix paid one instalment late, Yarn wrongly refused to deliver further instalments except for cash with each order, but offered to supply at the contract price on that basis. Wix refused, bought silk elsewhere at a higher price and claimed the difference. Which of the following best describes the position?

  1. Wix's damages are limited, as it unreasonably refused Yarn's offer.Correct answer
  2. Wix recovers the difference, because Yarn was not entitled to demand cash.
  3. Wix recovers nothing, because its late payment justified Yarn's demand.
  4. Wix recovers the difference, because it need not deal with the party in breach.
  5. Wix recovers the difference plus interest on the money it would have paid.
Question 10 · Damages: remoteness, causation and mitigationDraft, pending solicitor review

Zoe bought a house relying on her solicitor, Abe, who negligently failed to notice that the vendor's title was defective. As a result the house was worth less. Abe argues that Zoe should have mitigated her loss by suing the vendor under the covenants for title, a claim of uncertain outcome that would involve complex litigation. Which of the following best describes the position?

  1. Zoe's damages are reduced, because she failed to sue the vendor first.
  2. Zoe recovers nothing until she has exhausted her claim against the vendor.
  3. Zoe need not undertake complex, uncertain litigation to mitigate.Correct answer
  4. Zoe's damages are reduced by the value of her claim against the vendor.
  5. Zoe must sue the vendor, because a claimant must take every possible step.
Question 11 · Damages: remoteness, causation and mitigationDraft, pending solicitor review

Bel Bank's banknote printer, Cole Ltd, in breach of contract, allowed a fraudster to obtain a large number of notes. The bank, to maintain confidence in its currency, decided to honour all the fake notes presented, exchanging them for genuine notes. Cole argues that this was an excessive response and that the bank's loss was only the cost of printing replacement notes. Which of the following best describes the position?

  1. The bank recovers only the printing cost, because that was its true loss.
  2. The bank recovers the value of the notes honoured, as it acted reasonably.Correct answer
  3. The bank recovers nothing, because honouring fake notes was voluntary.
  4. The bank recovers only half its loss, because it chose an expensive response.
  5. The bank recovers the value only if it was legally obliged to honour them.
Question 12 · Damages: remoteness, causation and mitigationDraft, pending solicitor review

Dov, a subcontractor, was entitled under his contract with Eves Builders to be supplied with a stepladder. Eves failed to supply one. Dov chose instead to stand on an unfooted trestle, which slipped, and he was injured. He sues Eves for breach of contract, claiming damages for his injuries. Which of the following best describes the position?

  1. Eves is not liable, as its breach merely gave Dov the occasion.Correct answer
  2. Eves is liable, because its breach of contract led to Dov's injury.
  3. Eves is liable, but damages are reduced for Dov's contributory negligence.
  4. Eves is not liable, because personal injury cannot be claimed in contract.
  5. Eves is liable, because it should have foreseen Dov using unsafe equipment.
Question 13 · Damages: remoteness, causation and mitigationDraft, pending solicitor review

Fen Bank contracted with Gale Builders to clean and repair the roof of its warehouse, under a strict contractual obligation, not a duty of care. Gale's workers used a method that released asbestos dust, contaminating the building. Gale argues that Fen's damages should be reduced because Fen was itself careless in failing to supervise the work. Which of the following best describes the position?

  1. Fen's damages are reduced, because contributory negligence applies to all contracts.
  2. Fen's damages are reduced only if Fen's carelessness caused the release of dust.
  3. Fen's damages are reduced by half, because both parties were at fault.
  4. Fen's damages are not reduced, because a bank owes no duty to supervise.
  5. Fen's damages are not reduced, as Gale breached a strict obligation.Correct answer
Question 14 · Damages: remoteness, causation and mitigationDraft, pending solicitor review

Hari, a farmer, bought a towing hitch from a dealer, who warranted it was fit for use. The hitch's locking mechanism broke, and Hari, knowing it was broken, kept using it for several months. The trailer came loose and caused a fatal accident. Hari was held liable to the victims and sues the dealer for an indemnity for breach of warranty. Which of the following best describes the position?

  1. Hari recovers in full, because the hitch was not fit for use when sold.
  2. Hari recovers in full, because the warranty continued while he used the hitch.
  3. Hari recovers half, because both he and the dealer were at fault.
  4. Hari recovers nothing, as his knowing continued use broke the chain.Correct answer
  5. Hari recovers nothing, because warranties never cover liability to third parties.
Question 15 · Damages: remoteness, causation and mitigationDraft, pending solicitor review

Ida was employed as managing director of Jet Ltd on a five-year contract. Jet told her in advance that it would remove her from office in three months' time, in breach of contract. Ida did not accept the repudiation and insisted the contract continued. In the meantime she turned down another job offer. Jet argues that her damages should be reduced for failure to mitigate during that period. Which of the following best describes the position?

  1. Her damages are reduced, because she unreasonably refused the other job.
  2. Her damages are reduced, because she should have accepted the repudiation.
  3. Her damages are reduced, because mitigation applies from the date of the threat.
  4. No duty to mitigate ever arises for directors under fixed-term contracts.
  5. No duty to mitigate arose until she accepted the repudiation.Correct answer

More Contract Law topics

Back to all Contract Law questions, or sit a timed mock.