HomeContract LawFrustration

Contract Law · FLK1

Frustration: SQE1 practice questions

13 single best answer questions on frustration, with the answer explained and the law behind each one.

Practise Frustration

13 questions. Choose an answer, check it, and read the law behind it. Your place is saved in this browser.

Keyboard: press 1 to 5 (or A to E) to choose, Enter to check or continue.

Law covered in these questions

  • Taylor v Caldwell (1863) 3 B & S 826
  • Law Reform (Frustrated Contracts) Act 1943 s 1(2)
  • Krell v Henry [1903] 2 KB 740
  • Herne Bay Steam Boat Co v Hutton [1903] 2 KB 683
  • Davis Contractors Ltd v Fareham UDC [1956] AC 696
  • Tsakiroglou & Co Ltd v Noblee Thorl GmbH [1962] AC 93
  • Maritime National Fish Ltd v Ocean Trawlers Ltd [1935] AC 524
  • J Lauritzen AS v Wijsmuller BV (The Super Servant Two) [1990] 1 Lloyd's Rep 1
  • Condor v The Baron Knights Ltd [1966] 1 WLR 87
  • Law Reform (Frustrated Contracts) Act 1943, s 1(2)
  • Gamerco SA v ICM/Fair Warning (Agency) Ltd [1995] 1 WLR 1226
  • Law Reform (Frustrated Contracts) Act 1943, s 1(3)
  • BP Exploration Co (Libya) Ltd v Hunt (No 2) [1979] 1 WLR 783
  • Canary Wharf (BP4) T1 Ltd v European Medicines Agency [2019] EWHC 335 (Ch)

All 13 questions with answers

Try them above first, then read the worked answers below.

Question 1 · FrustrationDraft, pending solicitor review

Mina hired a concert hall from Hall Ltd for 1 June at a fee of £5,000 and paid a £2,000 deposit in advance. On 1 May, without fault on either side, the hall was destroyed by fire. Which statement best describes the position?

  1. The contract was void from the outset, so each party must return everything received under it.
  2. The contract was frustrated and automatically discharged from the date of the fire, and the deposit is recoverable subject to the court's power to allow Hall Ltd to retain expenses.Correct answer
  3. Hall Ltd is in breach of contract, and Mina can recover damages for the profit she expected from the concert.
  4. The contract is voidable at Mina's option, and Hall Ltd must provide an alternative venue.
  5. The contract remains binding until either party terminates it by notice, and the deposit is forfeited.
Question 2 · FrustrationDraft, pending solicitor review

Ola hired a music hall from Pip for four concerts. Before the first concert, and through no fault of either party, the hall was destroyed by fire. Ola had spent money advertising the concerts and sues Pip for breach of contract. The contract contained no express provision about destruction of the hall. Which of the following best describes the position?

  1. Pip is not liable, as the contract was frustrated by the hall's destruction.Correct answer
  2. Pip is liable, because the contract imposed an absolute duty to supply the hall.
  3. Pip is liable, because he bore the risk of fire as owner of the hall.
  4. Pip is not liable, because the contract was void for common mistake.
  5. Pip is liable for Ola's costs, but not for her lost profits.
Question 3 · FrustrationDraft, pending solicitor review

Quin hired a flat overlooking the route of a coronation procession for two days, for £75. The contract did not mention the procession, but both parties knew that viewing it was the reason for the hire. The procession was cancelled because of the king's illness. Rhian, the owner, claims the balance of the price. Which of the following best describes the position?

  1. Quin must pay, because the flat was still available for the two days.
  2. Quin must pay, because the procession was not mentioned in the contract.
  3. Quin need not pay the balance, as the contract was frustrated.Correct answer
  4. Quin need not pay, because Rhian misrepresented that the procession would occur.
  5. Quin must pay, but may claim damages for the cancellation from Rhian.
Question 4 · FrustrationDraft, pending solicitor review

Sol chartered a steamboat from Tug Ltd for two days 'for the purpose of viewing the naval review and for a day's cruise round the fleet'. The naval review was cancelled, but the fleet remained at anchor and the cruise round it could still take place. Sol refused to pay the hire, arguing that the contract was frustrated. Which of the following best describes the position?

  1. Sol need not pay, because the main purpose of the hire had failed.
  2. Sol need not pay, because the cancellation was outside both parties' control.
  3. Sol need not pay, because the naval review was expressly mentioned.
  4. Sol must pay half the hire, reflecting the part of the purpose remaining.
  5. Sol must pay, as the contract's foundation had not wholly failed.Correct answer
Question 5 · FrustrationDraft, pending solicitor review

Uno Builders agreed to build 78 houses for a council in eight months for a fixed price. Owing to unexpected shortages of skilled labour, the work took 22 months and cost far more than expected. Uno argued that the contract had been frustrated and claimed a reasonable sum for the work instead of the contract price. Which of the following best describes the position?

  1. The contract was frustrated, because performance became much more expensive.
  2. The contract was not frustrated, as it had merely become more onerous.Correct answer
  3. The contract was frustrated, because the delay was nearly three times longer.
  4. The contract was not frustrated, because building contracts cannot be frustrated.
  5. The contract was frustrated, because the labour shortage was not foreseeable.
Question 6 · FrustrationDraft, pending solicitor review

Vela Ltd agreed to sell groundnuts to Wing Ltd, shipment from Port Sudan to Hamburg in November. The contract did not specify the route. The usual route was via the Suez Canal, which was then closed by military action. Shipment via the Cape of Good Hope was possible but would take more than twice as long and cost twice as much. Vela refused to ship. Which of the following best describes the position?

  1. The contract was frustrated, because the agreed route had become impossible.
  2. The contract was not frustrated, because frustration never applies to sales of goods.
  3. The contract was frustrated, because the cost of shipment had doubled.
  4. The contract was not frustrated, as the Cape route was not radically different.Correct answer
  5. The contract was frustrated, because the parties had both assumed the canal route.
Question 7 · FrustrationDraft, pending solicitor review

Xeno Fishing chartered a trawler, the Yale, from Zeal Ltd for use with an otter trawl, which required a government licence. Xeno operated five trawlers and applied for five licences, but was granted only three. It chose to allocate the three licences to its own trawlers rather than to the Yale, and claimed the charter of the Yale was frustrated. Which of the following best describes the position?

  1. The charter was not frustrated, as the impossibility resulted from Xeno's own choice.Correct answer
  2. The charter was frustrated, because the licensing decision was outside Xeno's control.
  3. The charter was frustrated, because Xeno acted reasonably in favouring its own ships.
  4. The charter was not frustrated, because licensing changes are always foreseeable.
  5. The charter was frustrated, but Xeno must pay hire up to the date of the refusal.
Question 8 · FrustrationDraft, pending solicitor review

Ark Transport contracted to carry Bex's drilling rig using one of two vessels it owned, Ark choosing which. One vessel sank, without Ark's fault. Ark had already allocated its other vessel to other contracts and so told Bex that it could not perform. Ark claims the contract with Bex was frustrated. Which of the following best describes the position?

  1. The contract was frustrated, because the sinking occurred without Ark's fault.
  2. The contract was frustrated only in part, so Ark must pay half the price.
  3. The contract was frustrated, because Ark had to honour its other contracts.
  4. The contract was not frustrated, because carriage contracts cannot be frustrated.
  5. The contract was not frustrated, as Ark's own choice caused non-performance.Correct answer
Question 9 · FrustrationDraft, pending solicitor review

Cy, a drummer, agreed to play for a band on seven nights a week for five years. He became seriously ill, and his doctors advised that he could play no more than four nights a week, or he would risk a breakdown. The band dismissed him. Cy claims damages for wrongful dismissal. Which of the following best describes the position?

  1. The band is liable, because Cy's illness was temporary and he could still play.
  2. The band is not liable, as Cy's illness frustrated the contract.Correct answer
  3. The band is liable, because it should have reduced Cy's nights to four.
  4. The band is not liable, because Cy was in repudiatory breach by falling ill.
  5. The band is liable, because illness can never frustrate an employment contract.
Question 10 · FrustrationDraft, pending solicitor review

Dax Promotions agreed to promote a concert by a rock group at a stadium and paid the group an advance of £200,000. Before the concert, the stadium's safety licence was revoked and the concert could not go ahead. The contract was frustrated. The group had spent £40,000 on preparations. Dax claims repayment of the advance. Which of the following best describes the position?

  1. Dax recovers nothing, because losses lie where they fall on frustration.
  2. Dax recovers half the advance, because the losses are shared equally.
  3. Dax recovers the advance, subject to a discretionary allowance for expenses.Correct answer
  4. Dax recovers the advance less £40,000, because expenses must always be deducted.
  5. Dax recovers the advance only if there was a total failure of consideration.
Question 11 · FrustrationDraft, pending solicitor review

Elk Oil agreed to explore and develop an oilfield owned by Fern, in return for a share of the oil produced. Elk spent heavily and brought the field into production. Fern's government then expropriated the field, frustrating the contract. Fern had received some oil and compensation. Elk seeks a sum for the benefit it conferred. Which of the following best describes the position?

  1. Elk may recover a just sum, capped at the value of Fern's benefit.Correct answer
  2. Elk recovers nothing, because the contract was frustrated before it was paid.
  3. Elk recovers all the money it spent, regardless of any benefit to Fern.
  4. Elk recovers the value of its work as a quantum meruit at market rates.
  5. Elk recovers half its expenditure, because the risk is shared equally.
Question 12 · FrustrationDraft, pending solicitor review

Gala, an EU agency, held a 25-year lease of London offices. After the UK left the EU, Gala was required by EU law to relocate to Amsterdam and argued that the lease had been frustrated. The lease contained provisions for assignment and subletting, and Gala's relocation was a matter it could have anticipated to some extent. Which of the following best describes the court's likely view?

  1. The lease was frustrated, because Gala could no longer lawfully use the premises.
  2. The lease was frustrated, because leases are automatically ended by changes in law.
  3. The lease was not frustrated, as performance was not radically different.Correct answer
  4. The lease was not frustrated, because leases of land can never be frustrated.
  5. The lease was frustrated only for the remainder after Gala moved out.
Question 13 · FrustrationDraft, pending solicitor review

Hix Ltd held a 10-year lease of a warehouse. In year five, the council closed the only access road for 20 months because of a dangerous building nearby, preventing Hix from using the warehouse. Hix stopped paying rent, arguing that the lease had been frustrated. About three years of the lease would remain after the road reopened. Which of the following best describes the position?

  1. The lease was frustrated, because Hix could not use the warehouse at all.
  2. The lease was frustrated, but Hix must pay rent once the road reopened.
  3. The lease was frustrated, because the closure was caused by a public authority.
  4. The lease was not frustrated, because a lease of land can never be frustrated.
  5. The lease was not frustrated, given the length of the remaining term.Correct answer

More Contract Law topics

Back to all Contract Law questions, or sit a timed mock.