Discharge by performance and breach: SQE1 practice questions

16 single best answer questions on discharge by performance and breach, with the answer explained and the law behind each one.

Practise Discharge by performance and breach

16 questions. Choose an answer, check it, and read the law behind it. Your place is saved in this browser.

Keyboard: press 1 to 5 (or A to E) to choose, Enter to check or continue.

Law covered in these questions

  • Cutter v Powell (1795) 6 TR 320
  • Hoenig v Isaacs [1952] 2 All ER 176
  • Bolton v Mahadeva [1972] 1 WLR 1009
  • Sumpter v Hedges [1898] 1 QB 673
  • Sale of Goods Act 1979, s 30(1)
  • Planché v Colburn (1831) 8 Bing 14
  • Hochster v De la Tour (1853) 2 E & B 678
  • Avery v Bowden (1855) 5 E & B 714
  • White and Carter (Councils) Ltd v McGregor [1962] AC 413
  • Clea Shipping Corp v Bulk Oil International Ltd (The Alaskan Trader) [1984] 1 All ER 129
  • Vitol SA v Norelf Ltd (The Santa Clara) [1996] AC 800
  • Woodar Investment Development Ltd v Wimpey Construction UK Ltd [1980] 1 WLR 277
  • Charles Rickards Ltd v Oppenhaim [1950] 1 KB 616
  • Sale of Goods Act 1979, ss 11(4) and 35

All 16 questions with answers

Try them above first, then read the worked answers below.

Question 1 · Discharge by performance and breachDraft, pending solicitor review

Kurt agreed to serve as second mate on a voyage from Jamaica to Liverpool, to be paid 30 guineas 'provided he proceeds, continues and does his duty' until arrival. He served for seven weeks but died before the ship reached Liverpool. His widow claims a proportion of the wages for the time he served. Which of the following best describes the position?

  1. She can recover a proportion, because Kurt's death was not his fault.
  2. She cannot recover, as payment depended on complete performance.Correct answer
  3. She can recover a reasonable sum for the work Kurt actually did.
  4. She can recover the full 30 guineas, because death frustrated the contract.
  5. She cannot recover, because seamen's wages are payable only at sea.
Question 2 · Discharge by performance and breachDraft, pending solicitor review

Liam agreed to decorate Mona's flat and supply furniture for £750, payable 'net cash, as the work proceeds; and balance on completion'. He completed the work, but a wardrobe door needed replacing and a bookshelf was too short, costing about £56 to put right. Mona refused to pay the £350 balance, arguing that the work had not been completed. Which of the following best describes the position?

  1. Mona need pay nothing more, because the work was not fully completed.
  2. Liam can recover only a reasonable sum for the work done.
  3. Liam can recover the full balance, because the defects were minor.
  4. Mona need pay nothing more until Liam has fixed every defect.
  5. Liam can recover the balance less the cost of fixing the defects.Correct answer
Question 3 · Discharge by performance and breachDraft, pending solicitor review

Nell agreed to install a central heating system in Ola's house for £560. The system, when installed, gave out fumes that made the living room uncomfortable and heated the house unevenly, with temperatures varying by up to 15%. It would cost £174 to put right. Nell claims the price less £174. Which of the following best describes the position?

  1. Nell can recover the price less £174, under the substantial performance doctrine.
  2. Nell can recover the full price, because the system was installed and working.
  3. Nell cannot recover anything, as she did not substantially perform the contract.Correct answer
  4. Nell can recover a reasonable sum for the materials she supplied.
  5. Nell can recover half the price, as the system was half effective.
Question 4 · Discharge by performance and breachDraft, pending solicitor review

Pete agreed to build two houses on Quinn's land for £565. When he had done work worth about £333, he ran out of money and abandoned the job. Quinn finished the houses himself, using building materials Pete had left on site. Pete claims payment for the work done and the materials. Which of the following best describes Pete's position?

  1. He can recover for the materials used, but not for the work he did.Correct answer
  2. He can recover a reasonable sum for all the work done before he stopped.
  3. He can recover nothing, because Quinn completed the houses himself.
  4. He can recover the contract price less the cost of completing the houses.
  5. He can recover for the work done, but not for the materials left behind.
Question 5 · Discharge by performance and breachDraft, pending solicitor review

Raya Wholesale ordered 500 cases of olive oil from Sami Ltd at £20 a case. Sami delivered only 420 cases and could supply no more. Raya kept the 420 cases and sold most of them. Sami now claims payment for 420 cases. Raya argues that, as Sami failed to deliver the full quantity, it is not obliged to pay anything. Which of the following best describes the position?

  1. Raya need pay nothing, because the contract was for an entire quantity.
  2. Raya need pay nothing, unless it agreed to the short delivery in writing.
  3. Raya must pay a reasonable price for the 420 cases it kept.
  4. Raya must pay for the 420 cases at the contract rate.Correct answer
  5. Raya must pay the full price for 500 cases, less its damages.
Question 6 · Discharge by performance and breachDraft, pending solicitor review

Tara was engaged by a publisher to write a book for a series on armour, for £100 on completion. After she had researched and written part of the book, the publisher abandoned the series. Tara had not offered the partial manuscript and the publisher had not accepted it. Which of the following best describes Tara's position?

  1. She can recover nothing, because she did not complete the book.
  2. She can recover nothing, because the contract was frustrated.
  3. She can recover the full £100, because the publisher repudiated the contract.
  4. She can recover only if the publisher used the work she had done.
  5. She can recover a reasonable sum for the work done, on a quantum meruit.Correct answer
Question 7 · Discharge by performance and breachDraft, pending solicitor review

In April, Uma agreed to employ Vic as a tour courier from 1 June for three months. In May, Uma wrote to Vic saying she had changed her mind and would not need his services. Vic issued proceedings for damages on 22 May. Uma argues that Vic could not sue before 1 June, when performance was due. Which of the following best describes the position?

  1. Vic must wait until 1 June, because there can be no breach before performance is due.
  2. Vic may sue at once, as Uma's renunciation was an anticipatory breach.Correct answer
  3. Vic must wait until the end of the three months to know his loss.
  4. Vic may sue at once, but only for the first month's wages.
  5. Vic must first give Uma a reasonable opportunity to withdraw her letter.
Question 8 · Discharge by performance and breachDraft, pending solicitor review

Wren chartered Xan's ship to load cargo at Odessa within 45 days. Before the 45 days expired, Wren's agent told the ship's master that no cargo would be provided and advised him to leave. The master stayed, hoping a cargo might still come. Before the 45 days were up, war broke out, making loading illegal. Xan sues for breach. Which of the following best describes the position?

  1. Xan succeeds, because Wren's refusal was an anticipatory breach.
  2. Xan succeeds, because the master's decision to stay was reasonable.
  3. Xan fails, as he affirmed the contract and it was then frustrated.Correct answer
  4. Xan fails, because a charterer's refusal is never repudiatory.
  5. Xan succeeds, but only for the days the ship waited at Odessa.
Question 9 · Discharge by performance and breachDraft, pending solicitor review

Yell Ads agreed to display advertisements for Zed's garage on litter bins for three years. On the same day, before Yell had done anything, Zed cancelled. Yell refused to accept the cancellation, displayed the adverts for three years without needing Zed's cooperation, and sued for the full price under the contract. Which of the following best describes the position?

  1. Yell can recover only damages, because it should have mitigated its loss.
  2. Yell can recover only the price for the first year of advertising.
  3. Yell can recover nothing, because Zed had cancelled before performance began.
  4. Yell can recover the full price, having affirmed and performed.Correct answer
  5. Yell can recover the price only if Zed had expressly agreed to pay in advance.
Question 10 · Discharge by performance and breachDraft, pending solicitor review

Ark Shipping chartered a vessel to Bale Oil for 24 months. Halfway through, the engine failed and the charterers said they had no further use for the ship. Ark nonetheless spent £800,000 repairing the vessel and kept it fully crewed at anchor, unused, for the rest of the term, then claimed hire. Ark had no reason to keep the charter alive other than to claim hire. Which of the following best describes the position?

  1. Ark cannot recover hire, as it had no legitimate interest in affirming.Correct answer
  2. Ark can recover hire, because an innocent party may always affirm the contract.
  3. Ark can recover hire, because the charterers did not make a counter-offer.
  4. Ark cannot recover hire, because the engine failure frustrated the charter.
  5. Ark can recover hire, but only for the period the ship needed repairs.
Question 11 · Discharge by performance and breachDraft, pending solicitor review

Cova sold propane to Dart, delivery to be made in March. Dart wrongly told Cova that it was cancelling the contract. Cova said nothing in reply, but did not take the steps needed to deliver, such as issuing a bill of lading. Cova later sued for damages. Dart argued that Cova had never accepted its repudiation because Cova had not told Dart so. Which of the following best describes the position?

  1. Cova did not accept the repudiation, because acceptance must be in words.
  2. Cova did not accept the repudiation, because silence is never acceptance.
  3. Cova accepted the repudiation by its failure to perform.Correct answer
  4. Cova accepted the repudiation only once it issued legal proceedings.
  5. Cova did not accept the repudiation, so the contract remains in force.
Question 12 · Discharge by performance and breachDraft, pending solicitor review

Elm Developers agreed to buy land from Fir Estates. Elm, relying in good faith on its reasonable interpretation of a clause, served notice purporting to rescind the contract under that clause. A court later held that the clause did not in fact apply. Fir argues that Elm's notice was itself a repudiation entitling Fir to terminate and claim damages. Which of the following best describes the position?

  1. Elm repudiated, because wrongly purporting to rescind is always repudiatory.
  2. Elm did not repudiate, because land contracts cannot be repudiated.
  3. Elm repudiated, because a party must be certain before invoking a clause.
  4. Elm did not repudiate, as it relied on the clause in good faith.Correct answer
  5. Elm repudiated, but Fir may recover only nominal damages.
Question 13 · Discharge by performance and breachDraft, pending solicitor review

Gus ordered a custom car body from Hale Coachworks, to be delivered by 20 March. Hale missed the date. Gus continued to press for delivery for three months. In late June he wrote that, if the car was not ready within four weeks, he would cancel. It was not ready in time, and he cancelled. Which of the following best describes the position?

  1. Gus could not cancel, because he waived the original delivery date.
  2. Gus could cancel, having made time essential by notice.Correct answer
  3. Gus could not cancel, because time is never of the essence in a sale.
  4. Gus could cancel only if he paid for the work already done.
  5. Gus could not cancel, because four weeks was too short a period.
Question 14 · Discharge by performance and breachDraft, pending solicitor review

Ion Ltd bought a batch of steel pipes for its business from Jax Ltd. They were delivered in January. Ion inspected them, stored them and used some in its own projects. In September it discovered that they did not meet the required standard and sought to reject the entire batch. Which of the following best describes Ion's position?

  1. Ion may reject, because the breach of quality was a breach of condition.
  2. Ion may reject, provided it returns any unused pipes promptly.
  3. Ion may reject, because it discovered the defect only in September.
  4. Ion may not reject, because business buyers can never reject goods.
  5. Ion may not reject, as it is deemed to have accepted the goods.Correct answer
Question 15 · Discharge by performance and breachDraft, pending solicitor review

Kay and Lin entered into a partnership agreement containing a clause referring all disputes 'in respect of this agreement' to arbitration. Lin later repudiated the agreement, and Kay accepted the repudiation. When Kay sued for damages in court, Lin applied to stay the proceedings in favour of arbitration. Kay argued that the arbitration clause ended with the contract. Which of the following best describes the position?

  1. The clause survives, as it governs disputes arising from the breach.Correct answer
  2. The clause ended, because acceptance of repudiation discharges every term.
  3. The clause ended, because Lin cannot rely on a contract he repudiated.
  4. The clause survives, but only if Kay consents to arbitration.
  5. The clause ended, because the contract was treated as void from the outset.
Question 16 · Discharge by performance and breachDraft, pending solicitor review

Mio sold a consignment of rice to Nox Ltd for its business, payment due 30 days after delivery. Nox paid five days late. Market prices had risen, and Mio claimed to be entitled to treat the contract as repudiated and to recover the rice. The contract said nothing about whether time of payment was of the essence. Which of the following best describes the position?

  1. Mio may terminate, because prompt payment is always a condition.
  2. Mio may not terminate, unless the delay exceeded 30 days.
  3. Mio may terminate, because the market price had risen since delivery.
  4. Mio may not terminate, as time of payment is not essential.Correct answer
  5. Mio may terminate, because every late payment is a breach of warranty.